ASSESSMENT OF PROJECT PERFORMANCE: CASE OF 40/60 SAVING HOUSE DEVELOPMENT ENTERPRISE IN ADDIS ABABA BOLE AYAT LOT II
No Thumbnail Available
Files
Date
2018-10-22
Authors
Journal Title
Journal ISSN
Volume Title
Publisher
Hawassa University
Abstract
Construction industry has complexity in its nature because it contains large number of parties
as clients, contractors, consultants and other stakeholders. Construction projects suffer from
many problems and complex issues in performance such as cost, time and quality. The aim of
this thesis is to identify and evaluate the main factors affecting the performance of construction
projects in the case of Bole Ayat 40/60 condominium. Literature reviews about performance
were sited to identify the factors affecting the performance of construction projects. The
methodology/research design followed was descriptive research. A questionnaire survey was
conducted and 44 factors were identified, categorized, evaluated and ranked from small and
micro enterprises, client, consultants and contractors perspectives. The results were analyzed
and discussed to obtain the most performance indicators. The relative importance index (RII)
method was used here to determine perceptions of the relative importance of the performance
indicators in construction projects. The extremely significant factors affecting time performance
were shortage of material, financial problem and poor communication and coordination with
RII 0.75, 0.74 and 0.71 respectively. Whereas the factors affecting cost performance were
fluctuation in the cost of material, lack of cost planning and design change with RII 0.77, 0.693
and 0.691 respectively and factors affecting quality performance were educated and experienced
personnel, quality of materials and equipment used in the project with RII 0.81, 0.72 and 0.69
respectively. Recommendations were formulated to improve performance of construction
projects. It was concluded that every party participating on the project should have good
communication and coordination to avoid design discrepancies and disputes to improve
performance; they should have to hire qualified personnel to overcome any technical and
managerial problems
Description
Keywords
Project performance, cost, time, quality, 40/60 saving house development enterprise, condominium