INVESTIGATING SITE LAYOUT PLANNING AND IMPLEMENTATION PRACTICE IN BUILDING CONSTRUCTION PROJECTS
No Thumbnail Available
Date
2018-07-14
Authors
Journal Title
Journal ISSN
Volume Title
Publisher
Hawassa University
Abstract
Building projects in SNNPRS experience challenges of meeting project objectives due to an
improper initial work management plan, which includes a site layout planning. Lack of proper
site layout planning contributes to cost and time overruns in projects of the Region. Site layout
planning utilization has implications for project safety, construction efficiency, scheduling, and
budgetary performance of a project. The main purpose of this research was to investigate site
layout planning and implementation practice in building construction projects in SNNPRS. The
objectives of this study were identifying effects of poor site layout planning in building
construction activities, identifying the key factors which contribute to achieving an effective site
layout planning, and studying site layout plan utilization practice in building construction
projects in SNNPRS and finally to provide practical procedure that can be referenced when
developing site layout plan. The main approaches used in collecting information for the study
were through a questionnaire survey, and personal observations of some major construction sites
in SNNPRS in case of selected towns. The questionnaire survey was distributed to 40
respondents and a total of 36 responses were received. For the analysis of the data, statistical
analysis by using mean score ranking and descriptive statistics were employed. The finding of
the research indicated that the main impacts of poor site layout planning in building construction
activities were a decrease in the output from labour and machinery, construction materials lost
and damage, and increased travel distance on site. Availability of access and exit road to the
construction site, location of plant and equipment, and positioning of temporary facilities were
the major key factors which were found to be contributing to achieving an effective site layout
planning. In the research, site layout plan utilization practice in building construction projects
was also studied which led to development of a procedure describing an approach of site layout
plan in construction projects. The procedure incorporates important aspects associated with
project constraint identification, plan necessity, data acquisition, plan development,
communication, implementation and enforcement, monitoring and evaluating, and
documentation. This research contributes by providing information (factors) that one has to
examine in order to have an effective and efficient site layout planning and also by bringing
practical procedures and recommendations that can be referenced when developing site layout
plan on the construction site
Description
Keywords
Building projects, site layout planning, SNNPRS, temporary facilities